By using this site, you agree to the Privacy Policy and Terms of Use.
Accept
Daily MailDaily Mail
  • News
  • Politics
  • Crime
  • Metro
  • Opinion
  • Sports
  • Entertainment
  • Business
Reading: TCN Completes New Tower, Recovers Second 600mw Egbin-ajah Transmission Line
Share
Notification Show More
Font ResizerAa
Font ResizerAa
Daily MailDaily Mail
  • News
  • Politics
  • Crime
  • Metro
  • Opinion
  • Sports
  • Entertainment
  • Business
  • News
  • Politics
  • Crime
  • Metro
  • Opinion
  • Sports
  • Entertainment
  • Business
Have an existing account? Sign In
Follow US
  • News
  • Politics
  • Crime
  • Metro
  • Opinion
  • Sports
  • Entertainment
  • Business
© 2025 Daily Mail. Design By CrownTech. All Rights Reserved.
Daily Mail > Blog > News > TCN Completes New Tower, Recovers Second 600mw Egbin-ajah Transmission Line
News

TCN Completes New Tower, Recovers Second 600mw Egbin-ajah Transmission Line

Admin
Last updated: March 18, 2021 2:54 pm
Admin 4 years ago
Share
SHARE

The Transmission Company of Nigeria has completed the construction of a new transmission tower in Ajah, Lagos.

It has also strung the old and a new 330 kilovolts Egbin – Ajah transmission lines of which have been both energized.

This is contained in a statement signed by the General Manager, Public Affairs of the company, Ndidi Mba

The statement reeled out that, the new line increased the transmission lines capacity on that line route by 600 megawatts (MW) bringing it to a total of 1,200MW.

The statement added that while the old line was re-energized on Saturday 13th March, 2021 and the new line was energized on Monday 15th March, 2021.

It noted that prior to resuscitation of the second Egbin-Ajah Transmission Line, the Aja 330/132/33kV Substation operated through a single circuit 330kV transmission line, after the second line was isolated in 2013, due to Ajah GIS substation insulation failure. Within the period, the lone 330kV line had a maximum capacity of 600MW.

But with the resuscitation of the second 330kV line and the diversion of both lines along the new tower line route, the transmission lines capacity doubled.
With the new 330kV line, TCN has fulfilled the N-1 reliability criteria on that line route, providing redundancy.

Each of the line can serve as ‘back-up’ for the other during maintenance, this has increased transmission efficiency and reduced downtime on that line route.

The 13.8 kilometre transmission line receives power supply from Egbin 330kV Transmission Substation and supplies the Ajah 330kV Substation; Lekki 330kV Substation and Alagbon 330kV Transmission Substation.

The additional 330kV transmission line, equally means that more bulk power is now supplied to the substations of Eko Electricity Distribution Company taking supply form the listed transmission substations.

You Might Also Like

Go after financiers of insecurity, APC chieftain appeals to Tinubu, security agencies

Ede Poly Matriculates 11,508 Students As 583 Receive Student-Loan

May Day Celebration: Osun nulge President, Ogungbamigbe Hails Gov. Adeleke

Showers of Encomium As Ede Poly Former Rector, Bldr. Mosisyenemo Hussaini Celebrated

Gov Eno sparks Defection Rumour Plans

TAGGED: Power
Share This Article
Facebook Twitter Email Print
Previous Article Rotarian Ayodele Adeyemo Installed Asiwaju of Ogobi In Ede South LCDA
Next Article Barcelona will beat Chelsea to Man City’s greatest! – By Chris Beattiean
Leave a comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

about us

We influence 20 million users and is the number one business and technology news network on the planet.

Find Us on Socials

© 2025 Daily Mail. Design By CrownTech. All Rights Reserved.
Go to mobile version
Welcome Back!

Sign in to your account

Lost your password?